This project will involve:
- Creating a contiguous space by demolishing
- The Library’s former locked case
- The hallway wall, entrance to, and office within the former Book Repair Lab
- Necessary HVAC and fire sprinkler enhancements
- Replacing the ceiling and lighting
- Replacing the carpet
- Framing and sheetrocking the exterior walls
- Painting all walls
- Furnishing the space for student study
Ceiling demoed and east exterior wall framed Electrical work proceeding East and south walls sheetrocked Soffits between columns sheetrocked Mudding and taping of sheetrock proceeding Fire sprinkler work has begun HVAC & fire sprinkler work in progress Painting & additional HVAC work being done Work begins on ceiling grid Ceiling grid is complete and lights have been added Ceiling completed and painting done Room is carpeted and students have started using it Completed and furnished with furniture from Snack Zone